When a major catalog retailer needed to upgrade an entire call center
in two months, Sun Installed Base Business (IBB) consultants devised a
pricing and delivery strategy that gave the customer the necessary
competitive edge on-budget and on-time.
In July 2000, the catalog retailer
decided to upgrade their entire Ordering Control Center (OCC),
integrating the call center with their online operations, offering
customers new and improved services, and speeding the ordering
process. At first the task seemed daunting: Install 2000 workstations in 60 days,
and make sure users were proficient enough to handle the flood of new
business. They had a tight schedule and rigid budget requirements
Sun IBB sales staff devised a strict schedule to meet the start date
and then worked closely with Sun business units to ensure that everyone
stayed on course. The rigorous schedule was a success as IBB,
engineering, QA, and installation staff came together to meet the goal,
with two days to spare.
The Sun UltraTM workstations themselves helped meet the tight schedule.
System Administrators readily embraced the SolarisTM Operating
Environment (OE), making the conversion a seamless exercise.
Re-training costs were low, and the transition to the Sun Ultra 5
workstations was easy because users were already familiar with their
business applications and the Solaris OE. The new workstations and
operating environment provided them with the performance and capacity
to keep up with the holiday orders.
[...read more...]